| Project Summary |
Add
one general purpose lane and one auxiliary lane in each
direction adjacent to existing outside lanes. |
| Current
Development Phase |
Design
(as of February 2007) |
| Schedule |
RTP
Phase
1 to 2006-2010
Funding
accelerated by Valley Mayors - April 2006
Began Engineering and Environmental Study - July 2006
Complete Engineering
and Environmental Study - February 2007
Begin final design - Summer 2007
Complete final design - Spring 2008
Project Advertisement - Summer 2008
Begin construction - Mid 2009
Open to traffic - Summer 2010 |
 |